When the bulldozers finally reach the Chevy Chase library and community center, where does story time go? The city answered half of that question in writing before it had even picked a developer.
The project's request for proposals says a library must operate without interruption from the day the current branch closes until the new one opens. The rebuild is being planned around that one firm requirement. Each of the other open pieces, from the temporary library's location to the community center's interim home and the construction schedule, has to work around it. Two DC Council hearings this November and December will be the most formal look yet at how those pieces fit together.
What the city has committed to building
In January 2026, Mayor Muriel Bowser picked Rift Valley Chevy Chase, LLC to redevelop the Chevy Chase Civic Site, as The Wash and DMPED have both reported. The DC Public Library's project page names Studios Architecture as the design lead.
The DMPED project page lays out the swap building by building.
| Today | Planned | |
|---|---|---|
| Library | Built in 1968 | 23,500 square feet |
| Community center | Built in 1971 | 21,600 square feet |
| Outdoor space | Existing open space | More than double the existing open space |
| Public-facility parking | Current supply | More than 30 spaces, exceeding what is available now |
The plan also adds 177 homes and about 8,000 square feet of ground-floor retail that DMPED describes as community-serving. The outdoor plan is the part a regular visitor will notice most. DMPED lists a play park and public plaza, flexible sports and events courts, an amphitheater for performances and community events, a roof terrace with an outdoor classroom, and an oak lawn with a native plant garden. The 54 affordable units are split evenly between 30 percent and 50 percent of area median income, and the homes range from studios to three bedrooms. DMPED connects the site to the 2021 Comprehensive Plan and the 2022 Chevy Chase Small Area Plan. It also notes that the solicitation went through OurRFP, a process that asks residents for input before a request for proposals is issued.
The sentence that protects the library
The guarantee comes from the original RFP. The relevant passage reads:
"A library use is required to remain in continuous operation from the closure of the Library to the opening of the New Library ('Temporary Library Facility'). The Temporary Library Facility must be acceptable to DMPED and DCPL and included in Respondent's Proposal."
The same document requires a separate budget line for that temporary facility. It holds the developer responsible for cost overruns on the civic buildings, the temporary library included. The RFP also gives the public money behind each building. DCPL budgeted $24.2 million for the new library and the Department of Parks and Recreation budgeted $19.5 million for the new community center. Either agency may update those figures.
So the temporary library is written into the deal itself and cannot be dropped later as an afterthought. Its location has not been announced. DCPL's project page covers design work and community engagement, and the design process formally started with a June 9, 2026 kickoff. A street address for the interim branch is still to come.
The community center has no matching line
The RFP language on continuous operation covers only the library. DMPED's answers to ANC questions, updated June 3, 2026, say DPR's long-term plan is to expand programming once the new community center opens. The same document describes the project as early in design and does not set out where community center classes, meetings or recreation programs would go during construction.
That leaves the two buildings in different positions. Library patrons have a written requirement, a budget line and two agencies that must approve the interim site. Community center users have a plan to expand programs after the new building opens and no published arrangement for the construction years. That difference is the most concrete question residents can bring to the hearings below.
Where the next decisions happen
The disposition bill is B26-0801, the Chevy Chase Civic Site Surplus Declaration and Disposition Approval Act of 2026. The Council referred it to two committees, and each one is holding its own public hearing.
- October 27, 7 to 9 p.m. ANC 3/4G scheduled a special meeting devoted to the disposition of the Civic Core.
- Thursday, November 12, 10 a.m. The Committee on Human Services holds a public hearing on B26-0801, according to the Council's hearing notice.
- Thursday, December 3, 11 a.m. The Committee on Facilities holds a second public hearing on the same bill, per its separate notice.
The notices give the procedures for testifying. Someone who wants to ask about the temporary library site or interim community center programs will find the November and December hearings are the next public venues on the calendar.
How long the construction lasts
In the June FAQ, DMPED estimates construction at about 24 months, "consistent with other projects of this size and scale." The agency says the design is not yet far enough along for a detailed traffic analysis of the construction period. In September, The Wash reported that groundbreaking is expected in 2028. Neither source gives a firm completion date. If construction starts in 2028 and runs the estimated two years, the temporary library would serve the neighborhood for roughly that long. That figure is an inference from two estimates, not a schedule.
Construction would also add to work already planned for the avenue. DDOT's Connecticut Avenue multimodal safety project started intersection work in summer 2026 and expects it to take about two years. Its September 2026 status table shows Tilden Street under construction and the Chevy Chase/Harrison and Nebraska Avenue intersections still in procurement. In a September 30 report, NBC Washington said DDOT expects the intersection improvements to continue through 2027 and that bike lanes are not part of the plan.
Transit is the other variable. The Wash reported that the D70, which it describes as Connecticut Avenue's only Metrobus, was promised arrivals every 12 minutes or better at peak under WMATA's Better Bus Network, which launched June 29, 2025. The outlet's analysis of Transit App data found observed waits running closer to 30 minutes. It also quoted WMATA general manager Randy Clarke as saying, "We would not be adjusting service based on any new development." The location of the temporary library and of any interim community center programs will decide how much those bus waits matter to the people using them.
What a visit looks like until then
For now, nothing at the site has changed. The library and community center both remain in their 1968 and 1971 buildings while design continues. DMPED posts project documents, renderings and meeting materials on its Chevy Chase Civic Site page, and DCPL keeps its own project page on the library side. Any announcement of a temporary library location will likely appear on one of these two pages.
Plans for a public building at the center of Chevy Chase affect everything around it, from parking on Connecticut Avenue to the daily routines of the neighbors who use it. The Hagen Bergstrom Team follows projects like the Civic Core from the first hearing to the ribbon cutting. If you own nearby and want to talk through what the coming approvals and construction years could mean for your home, Book an Appointment with us.